    Eskom’s new generation unit added to fleet - ‘a milestone’ in efforts to stabilise power grid


    June 1, 2022 - Robin-Lee Francke

     

      Cape Town – Eskom announced on Wednesday that a generation unit at its Kusile Power Station had been transferred to its generation division to enter its commercial operation.

      It said Unit 4 at the power station was handed over to be formally part of the Eskom fleet on Tuesday.

      According to Eskom this is a milestone in its efforts to stabilise the power system in the country.

      The new generation unit will be adding a much-needed 800MW to the power system.

      “This milestone means the construction of four out of the six generation units have now been completed at the Kusile Power Station project. The Kusile project team and Eskom are working tirelessly to complete the rest of the project without any further delays as the country needs every megawatt of power it can get,” said Bheki Nxumalo, Eskom’s group executive for Capital Projects.

      The unit is said to have undergone a series of tests while intermittently supplying electricity over the past five months

      Since the unit’s synchronisation in December, Eskom said the unit had performed to expectations, intermittently sending up to 720MW and contributing to reducing load shedding.

      At completion, the power station will consist of six units which will produce 4 800MW.

      Units 5 and 6 will continue to progress according to plan with construction and commissioning activities.

      The Kusile Power Station is South Africa’s largest construction project and will be the world’s fourth-largest coal plant on completion.

      IOL

    TOP

    Other Articles - International


    TOP

       Home  -  Feedback  -  Contact Us  -  Safe Sender  -  About Energy Central   
    Copyright © 1996-2022 by CyberTech, Inc. All rights reserved.
    Energy Central® and Energy Central Professional® are registered trademarks of CyberTech, Incorporated. Data and information is provided for informational purposes only, and is not intended for trading purposes. CyberTech does not warrant that the information or services of Energy Central will meet any specific requirements; nor will it be error free or uninterrupted; nor shall CyberTech be liable for any indirect, incidental or consequential damages (including lost data, information or profits) sustained or incurred in connection with the use of, operation of, or inability to use Energy Central. Other terms of use may apply. Membership information is confidential and subject to our privacy agreement.