    Eskom making efforts to stabilise the power system


    June 1, 2022 - Ntombi Nkosi

     

      Power utility Eskom has announced that Unit 4 of the Kusile Power Station has been handed over to the Generation division as it enters commercial operation

      The utility which is currently the talk of the town amid a number of loadshedding said the move follows five months of vigorous testing and optimisation.

      Situated near eMalahleni in Mpumalanga, Kusile is South Africa’s largest construction project and will be the world’s fourth largest coal plant at completion.

      Eskom said the project was on Tuesday handed over to the Generation division to formally be part of the Eskom commercial fleet.

      This utility said the the handover marks another milestone in It’s fforts to stabilise the power system in that it has formally added a much needed 800MW to the country’s power system. The unit was connected to the national grid for the first time on 23 December 2021.

      “This milestone means the construction of four out of the six generation units have now been completed at the Kusile Power Station project. The Kusile project team and Eskom are working tirelessly to complete the rest of the project without any further delays as the country needs every megawatt of power it can get,” said Bheki Nxumalo, the Eskom Group Executive for Capital Projects.

      Nxumalo exoressed appreciation to the utility’s guardians and contractors who worked tirelessly to deliver the unit to its successful commercial operation.

      He said the unit has undergone a series of tests while intermittently supplying electricity over the past five months. “Since synchronization in December 2021, the unit has performed to expectation, intermittently sending up to 720MW and contributing to reducing the implementation of loadshedding.

      “At completion, the station will consist of six units, and will produce a maximum 4 800MW. Construction and commissioning activities on the remaining Kusile Units 5 and 6 continue to progress according to plan,” Nxumalo said.

      He said Eskom is fitting wet flue gas desulphurisation (WFGD) to the Kusile plant as an atmospheric emission abatement technology, in line with current international practice, to ensure compliance with air quality standards, making it more environmentally friendly.

      Nxumalo said Kusile is the first power station in South Africa and Africa to use WFGD technology.

      WFGD is the state-of-the-art technology used to remove oxides of sulphur (SOx), for example sulphur dioxide (SO2) in the emissions of power plants that burn coal or oil.

      ntombi.nkosi@inl.co.za

    TOP

    Other Articles - International


    TOP

       Home  -  Feedback  -  Contact Us  -  Safe Sender  -  About Energy Central   
    Copyright © 1996-2022 by CyberTech, Inc. All rights reserved.
    Energy Central® and Energy Central Professional® are registered trademarks of CyberTech, Incorporated. Data and information is provided for informational purposes only, and is not intended for trading purposes. CyberTech does not warrant that the information or services of Energy Central will meet any specific requirements; nor will it be error free or uninterrupted; nor shall CyberTech be liable for any indirect, incidental or consequential damages (including lost data, information or profits) sustained or incurred in connection with the use of, operation of, or inability to use Energy Central. Other terms of use may apply. Membership information is confidential and subject to our privacy agreement.