ST. PAUL, Minnesota, June 7 (TNSsro) -- The Minnesota Utilities Commission issued the following decision involving Xcel Energy and Minnesota Investor-Owned Electric Utilities:
INTRODUCTION
DECISION ITEMS
1. Details 2019-098
* E002/RP-19-368
Xcel Energy
In the Matter of Xcel Energy's 2020-2034 Integrated Resource Plan.
Should the Commission approve the Xcel Energy request to amend the April 15, 2022 Order in this docket at Order Point 2.A.1 as follows: Each year through 2034, Xcel shall save, on average, at least 780 gigawatt-hours via energy efficiency. (PUC: Stalpes)
Attachments: Xcel Petition (http://minnesotapuc.legistar.com/gateway.aspx?M=F&ID=76623299-03ad-4efa-88c6-9c3303929e8f.pdf)
2. Details 2022-060
** E999/CI-20-800; E002/M-19-685
Minnesota Investor-Owned Electric Utilities
In the Matter of a Commission Investigation on Grid and Customer Security Issues Related to Public Display or Access to Electric Distribution Grid Data.
What, if any, action by the Commission is needed to address electric distribution grid and customer security issues related to public display or access to grid data; including, but not limited to, distribution grid mapping, aggregated load data, and critical infrastructure? (PUC: Noyce, Rosier)
Attachments: Briefing Papers (http://minnesotapuc.legistar.com/gateway.aspx?M=F&ID=e22cc148-fbdc-4184-80d1-d9e1adf57f0c.pdf)
ADJOURNMENT
* One star indicates agenda item is unusual but is not disputed.
** Two stars indicate a disputed item or significant legal or procedural issue to be resolved. (Ex Parte Rules apply)
Please note: For the complete record, please see eDockets