    NRC Launches Special Inspection at Farley Nuclear Power Plant


    August 11, 2022 - Targeted News Service

     

      WASHINGTON, Aug. 11 -- The Nuclear Regulatory Commission issued the following news release:

      The Nuclear Regulatory Commission has launched a special inspection at Unit 1 of the Joseph M. Farley nuclear power plant due to a partial loss of off-site power and subsequent issues with a turbine-driven auxiliary feed pump.

      The two-unit Farley plant is located in southern Alabama and is operated by Southern Nuclear Operating Company. Unit 2 was not affected.

      On Aug. 3, Unit 1 automatically shut down due to the partial loss of offsite power. One of the emergency power buses, which provides electricity to safety equipment, also lost power. The plant's emergency diesel generator automatically started, restoring power to the emergency bus, and the auxiliary feed system provided reactor cooling, as designed, placing the plant in a safe condition.

      A short time later, while operators were shutting down the turbine-driven auxiliary feed pump, which was no longer needed, the pump automatically restarted and subsequently tripped. Operators then declared the pump inoperable.

      "While this event didn't present a threat to public health and safety, because redundant systems ensured the plant was safely shutdown, we want to independently gather additional information on what happened and why it happened," said Region II Administrator Laura Dudes. "We'll also assure the company is taking comprehensive steps to prevent recurrence."

      NRC resident inspectors, permanently stationed at the Farley plant, responded to the control room during the event and independently monitored plant conditions, reviewed the company's initial corrective actions, and monitored the plant restart several days after the automatic shutdown.

      The inspection report will be issued about 45 days after the inspection is completed and will be available on the NRC website (https://www.nrc.gov/).

      * * *

      Original text here: https://www.nrc.gov/cdn/doc-collection-news/2022/22-021-ii.pdf

    TOP

    Other Articles - Generation


    TOP

       Home  -  Feedback  -  Contact Us  -  Safe Sender  -  About Energy Central   
    Copyright © 1996-2022 by CyberTech, Inc. All rights reserved.
    Energy Central® and Energy Central Professional® are registered trademarks of CyberTech, Incorporated. Data and information is provided for informational purposes only, and is not intended for trading purposes. CyberTech does not warrant that the information or services of Energy Central will meet any specific requirements; nor will it be error free or uninterrupted; nor shall CyberTech be liable for any indirect, incidental or consequential damages (including lost data, information or profits) sustained or incurred in connection with the use of, operation of, or inability to use Energy Central. Other terms of use may apply. Membership information is confidential and subject to our privacy agreement.