    EirGrid consultation for East Meath-North Dublin Grid Upgrade


    September 9, 2022 - Ken Phelan

     

      EirGrid, the operator and developer of the national electricity grid, is seeking the public’s input in identifying a route for the East Meath-North Dublin Grid Upgrade.

      The 400kV underground cable circuit from Woodland substation, near Batterstown in County Meath, to Belcamp substation, near Clonshaugh in north Dublin, was identified earlier this year as the best-performing technical option.

      The project is needed to address the increased electricity demand in east Meath and north Dublin, due to economic activity and population growth, while also reducing the use of fossil fuels for electricity generation.

      When developed, the upgrade will improve electricity supply in the region.

      EirGrid will consult with the public over the next 12 weeks to identify where the circuit should be built.

      The consultation will include information days, open days and webinars, where the EirGrid project team will provide information about four proposed route options.

      EirGrid’s Chief Infrastructure Officer, Michael Mahon said: “This upgrade is essential to strengthen the grid as our society and economy grows, and as the electrification of heat and transport increases.

      "This upgrade will also help to achieve our renewable ambition as we prepare the grid for the future development of renewable energy.

      “This 12-week consultation will give communities and stakeholders across the proposed study area the opportunity to ask questions about the routes and share their views on a preferred option.

      "We look forward to consulting with communities and stakeholders in east Meath and north Dublin over the coming weeks.”

      A community forum has been established to ensure that stakeholder and community views are understood and properly considered.

      The forum will act as a consultative body providing feedback at key stages in the delivery of the project.

      To find out more about the four proposed routes, visit eirgrid.ie/EastMeathNorthDublin.

      EirGrid develops and operates the national electricity grid, so that everyone has power when and where they need it.

      The grid takes electricity from where it is generated and delivers it to the distribution network, operated by ESB, which powers every home, business, school, hospital, factory and farm on the island.

      Eirgrid also supplies power directly to some of Ireland’s largest energy users. It is responsible for a safe, secure and reliable supply of electricity, now and in the future.

    TOP

    Other Articles - International


    TOP

       Home  -  Feedback  -  Contact Us  -  Safe Sender  -  About Energy Central   
    Copyright © 1996-2022 by CyberTech, Inc. All rights reserved.
    Energy Central® and Energy Central Professional® are registered trademarks of CyberTech, Incorporated. Data and information is provided for informational purposes only, and is not intended for trading purposes. CyberTech does not warrant that the information or services of Energy Central will meet any specific requirements; nor will it be error free or uninterrupted; nor shall CyberTech be liable for any indirect, incidental or consequential damages (including lost data, information or profits) sustained or incurred in connection with the use of, operation of, or inability to use Energy Central. Other terms of use may apply. Membership information is confidential and subject to our privacy agreement.