    Oracle Power: LOI Issued for 1,200MW Power/Green Hydrogen Project


    September 15, 2022 - Contify Energy News

     

      Oracle Power PLC, the international natural resources project developer, is pleased to announce that further to the announcement of 1 September 2022, the Company's joint venture company, Oracle Energy Limited ("Oracle Energy" or the "Joint Venture"), has been issued a Letter of Intent ("LOI") from the Directorate of Alternative Energy of the Government of Sindh (the "Directorate of Alternative Energy"), relating to the establishment of a 1,200MW hybrid solar/wind, green hydrogen/power project (the "Project") in Pakistan. The issuance of the LOI follows the Directorate of Alternative Energy's confirmation of receipt of a $600,000 bank guarantee (the "Bank Guarantee") from Habib Metropolitan Bank, Karachi ("Habib Metropolitan") valid for 12 months, on behalf of Oracle Energy.

      Key Highlights:

      * The LOI sets out that the developer of the Project can produce green hydrogen from a 400MW capacity electrolyser facility and renewable power for business-to-business usage, for possible sale to utilities and for other uses.

      * In accordance with the LOI, Oracle Energy is required to complete certain milestones in the next 18 months which include, inter alia, feasibility and environmental studies, securing water use agreements, completing grid studies for interconnection, obtaining a tariff from the National Electric Power Regulatory Authority ("NEPRA") if required, providing a further bank guarantee of US$3 million and receiving a Letter of Support from the Directorate of Alternative Energy.

      * Provided the required milestones have been met by Oracle Energy up to that time, the LOI can be extended beyond the initial 18 months, in the event that the relevant regulator fails to announce or award a tariff due to delays on the account of Government processes.

      * Extensions can be repeatedly provided for six months at a time and during any period of extension, if the tariff is awarded, Oracle Energy is required to obtain a Letter of Support by submitting the required further US$3 million bank guarantee.

      Original Press Release:

      Sept. 15 -- Oracle Power PLC issued the following news release:

      Oracle Power PLC (AIM:ORCP), the international natural resources project developer, is pleased to announce that further to the announcement of 1 September 2022, the Company's joint venture company, Oracle Energy Limited ("Oracle Energy" or the "Joint Venture"), has been issued a Letter of Intent ("LOI") from the Directorate of Alternative Energy of the Government of Sindh (the "Directorate of Alternative Energy"), relating to the establishment of a 1,200MW hybrid solar/wind, green hydrogen/power project (the "Project") in Pakistan. The issuance of the LOI follows the Directorate of Alternative Energy's confirmation of receipt of a $600,000 bank guarantee (the "Bank Guarantee") from Habib Metropolitan Bank, Karachi ("Habib Metropolitan") valid for 12 months, on behalf of Oracle Energy.

      Highlights / Key Terms of the LOI

      * The LOI sets out that the developer of the Project can produce green hydrogen from a 400MW capacity electrolyser facility and renewable power for business-to-business usage, for possible sale to utilities and for other uses.

      * In accordance with the LOI, Oracle Energy is required to complete certain milestones in the next 18 months which include, inter alia, feasibility and environmental studies, securing water use agreements, completing grid studies for interconnection, obtaining a tariff from the National Electric Power Regulatory Authority ("NEPRA") if required, providing a further bank guarantee of US$3 million and receiving a Letter of Support from the Directorate of Alternative Energy.

      * Oracle's share of the funding requirement for these milestones will be from current cash and additional funding as required during the course of development.

      * Provided the required milestones have been met by Oracle Energy up to that time, the LOI can be extended beyond the initial 18 months, in the event that the relevant regulator fails to announce or award a tariff due to delays on the account of Government processes. Extensions can be repeatedly provided for six months at a time and during any period of extension, if the tariff is awarded, Oracle Energy is required to obtain a Letter of Support by submitting the required further US$3 million bank guarantee.

      * Oracle Energy will also coordinate with a panel of experts from the Directorate of Alternative Energy to determine site layout, sub-station design, transmission line, interconnection arrangements and other related operational and technical matters.

      * The Directorate of Alternative Energy may terminate the LOI and encash the Bank Guarantee if, inter alia, the requisite milestones are not met, or the Bank Guarantee is not extended.

      The Bank Guarantee provided by Habib Metropolitan on behalf of Oracle Energy is valid for 12 months; however, Oracle Energy has been advised by Habib Metropolitan that the guarantee can be extended at Habib Metropolitan's discretion and subject to certain terms.

      Naheed Memon, CEO of Oracle, commented:

      "This LOI gives us the confidence to move forward determinedly with our pioneering green hydrogen project in Pakistan. With the support of the Directorate of Alternative Energy, and of course our joint venture partner, His Highness Shaikh Ahmed Dalmook Al Maktoum, we are in a solid position to make material progress with our plans to establish a hybrid solar/wind, green hydrogen/power project of up to 1,200MW in a rapid timeframe.

      "As we look now to the milestones set out in the LOI, including relevant studies and securing required infrastructure we will, in parallel, look to deliver and expand our commercial initiatives to ensure we have a comprehensive and wide-ranging array of options to maximise value for investors, and commercialise this transformative energy source. I look forward to providing updates on our progress in this regard over the coming weeks and months."

      About Oracle Power PLC:

      Oracle Power PLC is an international natural resource and power project developer quoted on London's AIM market. The Company currently has two areas of focus: Western Australia and Pakistan. The Company is active in the energy industry in Pakistan and is working to establish a green hydrogen production facility through Oracle Energy Limited, a joint venture with His Highness Shaikh Ahmed Dalmook Al Maktoum. The Company's initial project is the Thar Block VI Project in south-east Pakistan where the Company is advancing plans for a combined lignite coal mine, a 1,320MW mine mouth power plant and a proposed coal gasification to urea project.

      In Australia, its primary focus is the Northern Zone Gold Project, located 25km east of the major gold mining centre of Kalgoorlie, the home of the 'Super Pit' mine, the second largest gold mine in Australia. Northern Zone has a current Exploration Target of 200-250Mt at 0.4-0.6g/t Au for between 2.5 - 4.8Moz gold, with drilling being planned to define a maiden inferred JORC resource.

      Source: Oracle Power PLC

      [Category: Power, Power Generation]

    TOP

    Other Articles - International


    TOP

       Home  -  Feedback  -  Contact Us  -  Safe Sender  -  About Energy Central   
    Copyright © 1996-2022 by CyberTech, Inc. All rights reserved.
    Energy Central® and Energy Central Professional® are registered trademarks of CyberTech, Incorporated. Data and information is provided for informational purposes only, and is not intended for trading purposes. CyberTech does not warrant that the information or services of Energy Central will meet any specific requirements; nor will it be error free or uninterrupted; nor shall CyberTech be liable for any indirect, incidental or consequential damages (including lost data, information or profits) sustained or incurred in connection with the use of, operation of, or inability to use Energy Central. Other terms of use may apply. Membership information is confidential and subject to our privacy agreement.