    Danish Authorities Order Ørsted’s Oil- and Coal-Fired Power Stations into Operation


    October 2, 2022 - Gulf Oil & Gas

     

      In order to ensure the security of the electricity supply in Denmark, the Danish authorities have decided to order Ørsted to continue and resume operations of three of its power station units which use oil and coal as fuel.

      This applies to unit 3 at Esbjerg Power Station and unit 4 at Studstrup Power Station, which both use coal as their primary source of fuel, and unit 21 at Kyndby Peak Load Plant, which uses oil as fuel. The two latter units have already been decommissioned and preserved, whereas Esbjerg Power Station was scheduled to be decommissioned on 31 March 2023.

      Mads Nipper, Group President and CEO of Ørsted, says:

      "In order to ensure the security of the electricity supply, the Danish authorities have today ordered us to continue as well as resume operations at some of our oil- and coal-fired power stations. We will, of course, comply with the Danish authorities’ order, and we'll now begin preparing and maintaining the units as well as securing the staffing necessary to operate them. We still believe that we, as a society, must phase out the use of gas, oil, and coal as soon as possible, but we're in the middle of a European energy crisis, and we will, of course, contribute to ensuring the electricity supply to the best of our ability."

      Ørsted will be facing a number of technical and staffing issues that will have to be solved. Maintenance will have to be carried out at all three units to prepare them for operation during the required period. In addition, it takes highly specialised workers to operate a power station, and they must be trained in operating the specific power station. Ørsted expects that it will take time to get everything in place, especially for unit 4 at Studstrup Power Station and unit 21 at Kyndby Peak Load Plant, but will make every effort to get the units ready for operation as soon as possible.

      The Danish authorities have ordered Ørsted to keep the three units in operation until 30 June 2024, and Ørsted therefore maintains its goal of becoming carbon-neutral by 2025.

    TOP

    Other Articles - International


    TOP

       Home  -  Feedback  -  Contact Us  -  Safe Sender  -  About Energy Central   
    Copyright © 1996-2022 by CyberTech, Inc. All rights reserved.
    Energy Central® and Energy Central Professional® are registered trademarks of CyberTech, Incorporated. Data and information is provided for informational purposes only, and is not intended for trading purposes. CyberTech does not warrant that the information or services of Energy Central will meet any specific requirements; nor will it be error free or uninterrupted; nor shall CyberTech be liable for any indirect, incidental or consequential damages (including lost data, information or profits) sustained or incurred in connection with the use of, operation of, or inability to use Energy Central. Other terms of use may apply. Membership information is confidential and subject to our privacy agreement.