    US$125 Million to Upgrade Cahora Bassa Hydroelectric Plant


    December 2, 2022 - Financial Services Monitor Worldwide

     

      The Board of Directors of the African Development Bank (AfDB) Group has approved a US$ 125 million loan for the modernisation of the Cahora Bassa hydroelectric scheme in Mozambique. Its power plant has an installed capacity of 2,075 MW.

      Good news for Hidroelctrica de Cahora Bassa (HCB). The company that operates the Cahora Bassa hydroelectric scheme in Mozambique has just obtained a $125 million loan from the African Development Bank (AfDB). The recently approved funding is provided by the AfDB ($100 million) and the Growing Together in Africa Fund, a $2 billion facility funded by the Peoples Bank of China (PBC) and administered by the AfDB.

      The funding is for the implementation of the Vital Capex programme to upgrade its power generation system. The Cahora Bassa hydroelectric scheme consists of a 171m high, 300m long dam on the Zambezi River. The dam allows for the operation of a power plant with five 415 MW turbines, giving an installed capacity of 2,075 MW. It is the second largest operational hydroelectric plant in Africa after the Aswan plant in Egypt, with a capacity of 2,100 MW.

      Since the plant was commissioned between 1976 and 1979, HCB has been selling electricity to the state-owned Electricidade de Moambique (EDM) and to the Southern African Development Community (SADC), including South Africa, Zambia and Botswana. According to the company, which is based near the Cahora Bassa dam in the village of Songo, Tete province, the modernisation of its production facilities will extend the life of the plant by at least 25 years.

      According to him, the Vital Capex programme will also improve the reliability of power supply, reduce outages, enable the company to meet its contractual obligations to its suppliers and enhance regional integration of the power sector within SADC. The programme will also ensure the sustainability of energy security in SADC, particularly in South Africa, Mozambique and Zimbabwe, the AfDB says.

      The contract for the rehabilitation of the Cahora Bassa hydropower plant was awarded in 2019 to a consortium including Sweco, an architectural firm based in Stockholm, Sweden and Intertechne Consultores, a company based in Curitiba, Brazil. The rehabilitation work should be completed in 2025.

    TOP

    Other Articles - International


    TOP

       Home  -  Feedback  -  Contact Us  -  Safe Sender  -  About Energy Central   
    Copyright © 1996-2023 by CyberTech, Inc. All rights reserved.
    Energy Central® and Energy Central Professional® are registered trademarks of CyberTech, Incorporated. Data and information is provided for informational purposes only, and is not intended for trading purposes. CyberTech does not warrant that the information or services of Energy Central will meet any specific requirements; nor will it be error free or uninterrupted; nor shall CyberTech be liable for any indirect, incidental or consequential damages (including lost data, information or profits) sustained or incurred in connection with the use of, operation of, or inability to use Energy Central. Other terms of use may apply. Membership information is confidential and subject to our privacy agreement.