TEPCO has made the changes to the transport schedule for low-level radioactive waste in the "FY2022 Transport Schedule for New Fuels at Hamaoka Nuclear Power Station" announced on March 30, 2022.
Original Press Release:
Jan. 17 -- Chubu Electric Power Co., Inc. issued the following news release:
TEPCO has made the following changes to the transport schedule for low-level radioactive waste in the "FY2022 Transport Schedule for New Fuels at Hamaoka Nuclear Power Station" announced on March 30, 2022.
Low level radioactive waste
Disclaimer: Table can be viewed at: https://www.chuden.co.jp/publicity/press/1210027_3273.html
A self-inspection of the low-level radioactive waste (1,488 drums) that was scheduled to be transported was being conducted at the Hamaoka Nuclear Power Station. Since we were unable to inspect the quantity, we decided to transport 1,264 drums that had completed our self-inspection.
Disclaimer: The Above Content is Auto-Translated
Source: Chubu Electric Power Co., Inc.