    Load shedding to alternate between stages 3 and 4 this week


    February 6, 2023 - Citizen Reporter

     

      South Africa's load shedding is practically permanent now with the only change being what stage of load shedding the country finds itself in at any given moment.

      Here's what to expect this coming week

      Expect Stages 3 and 4 between Monday and Wednesday

      According to a statement issued by Eskom on Sunday, Stage 3 load shedding will be implemented at 5 am on Monday and will continue until 4 pm daily, while Stage 4 will be implemented nightly from 4 pm until 5 am on both Monday and Tuesday.

      "On Wednesday Stage 2 load shedding will be implemented at 5 am until 4 pm followed by Stage 3 at 4 pm until 5 am. A further update will be published as soon as any significant changes occur."

      The announcement comes after a weekend of Stage 2 load shedding.

      Two units taken offline for repairs

      The power utility further explained that since Saturday two generation units at Arnot, a single unit each at Camden, Duvha and Kendal power stations were taken offline for repairs.

      READ MORERobberies surge as criminals take advantage of load shedding

      "The return to service of a generation unit each at Kendal and Lethabo power stations have been delayed while a unit each at Duvha and Lethabo power stations were returned to service."

      "Breakdowns currently amount to 15 215MW of generating capacity while 5 199MW of generating capacity is out of service for planned maintenance."

      According to the power utility, load shedding is implemented to protect the national electricity network by balancing supply and demand.

      "If this is not done, the national grid will shut down entirely and the entire country will be blacked out for days to weeks."

    TOP

    Other Articles - International


    TOP

       Home  -  Feedback  -  Contact Us  -  Safe Sender  -  About Energy Central   
    Copyright © 1996-2023 by CyberTech, Inc. All rights reserved.
    Energy Central® and Energy Central Professional® are registered trademarks of CyberTech, Incorporated. Data and information is provided for informational purposes only, and is not intended for trading purposes. CyberTech does not warrant that the information or services of Energy Central will meet any specific requirements; nor will it be error free or uninterrupted; nor shall CyberTech be liable for any indirect, incidental or consequential damages (including lost data, information or profits) sustained or incurred in connection with the use of, operation of, or inability to use Energy Central. Other terms of use may apply. Membership information is confidential and subject to our privacy agreement.