SA back to Stage 4 load shedding as units trip at Kendal, Lethabo power stations


Molaole Montsho  

 

    Johannesburg - Eskom has escalated load shedding back to Stage 4 after generation units tripped at Kendal and Lethabo power stations on Tuesday.

    “A generation unit each at Kendal and Lethabo power stations have just tripped. This necessitates the immediate escalation of load shedding to stage 4 at 18:00. This stage of load shedding will be maintained until further notice,” Eskom said.

    Eskom spokesperson Sikhonathi Matshantsha said the power utility would publish a full statement on Wednesday afternoon.

    The power utility had said this week that Stage 3 load shedding would be maintained until Thursday morning.

    Eskom said the continued load shedding was necessary due to the shortage of generation capacity as a result of persistent high levels of breakdowns.

    Energy experts have warned that the situation could get worse if nothing was done.

    “This year we got Stage 6 and it could be higher if we do not do something about it,” said energy analyst Chris Yelland.

    “The President (Cyril Ramaphosa) has given a whole plan of action. We need to implemented that plan, we need to stop talking about that plan. The plan is on the table, the national emergency crisis committee has been established, there are number of work streams, they are looking at different aspects of that plan and it needs to be implemented fast.”

    Part of Ramaphosa’s emergency energy plan, which was presented to the public in July, includes importing power from neighbouring countries in the SADC region, as well as procuring power from private players.

    IOL

TOP


Copyright © 1996-2023 by CyberTech, Inc. All rights reserved.
Energy Central® and Energy Central Professional® are registered trademarks of CyberTech, Incorporated. Data and information is provided for informational purposes only, and is not intended for trading purposes. CyberTech does not warrant that the information or services of Energy Central will meet any specific requirements; nor will it be error free or uninterrupted; nor shall CyberTech be liable for any indirect, incidental or consequential damages (including lost data, information or profits) sustained or incurred in connection with the use of, operation of, or inability to use Energy Central. Other terms of use may apply. Membership information is confidential and subject to our privacy agreement.