    New German-Austrian grid connection to spur renewables integration


    March 13, 2023 - SeeNews Renewables

     

      March 13 (Renewables Now) - Transmission system operators Austrian Power Grid AG (APG) and TenneT have broken the ground on a project for the construction of a power line between Germany and Austria that will enable wind power transmission from northern Europe to pumped storage plants in the Alps.

      The new 380 kV line will run from St. Peter am Hart in Upper Austria to Altheim in Bavaria. It will connect APG's grid node in St. Peter with the TenneT substations in Simbach, Ottenhofen, Isar and Pleinting in Bavaria.

      The interconnector, which is designated as a project of common interest (PCI), is planned to be operational in 2027.

      The construction of the new line is part of the efforts to better integrate Austria into the European electricity market. The 380 kV line will ensure more security by providing Austrian electricity consumers with better access to the European power market, according to APG's chief technology officer Gerhard Christiner.

      The two existing 220 kV lines from St. Peter to Bavaria were built in the 1940s and 1960s and their capacity is not enough to meet the growing renewable energy needs in the course of the energy transition. In addition, the lack of grid capacity also prevents the supply of clean electricity from Germany to Austrian electricity consumers.

      Christiner noted that the high number of redispatch measures is not only a warning that the exiting power lines are reaching their capacity limits but also a financial burden for all consumers. In 2022 alone, the costs for redispatch measures in this area amounted to EUR 718 million (USD 760.07m), Christiner added.

      (EUR 1 = USD 1.059)

    TOP

    Other Articles - International


    TOP

       Home  -  Feedback  -  Contact Us  -  Safe Sender  -  About Energy Central   
    Copyright © 1996-2023 by CyberTech, Inc. All rights reserved.
    Energy Central® and Energy Central Professional® are registered trademarks of CyberTech, Incorporated. Data and information is provided for informational purposes only, and is not intended for trading purposes. CyberTech does not warrant that the information or services of Energy Central will meet any specific requirements; nor will it be error free or uninterrupted; nor shall CyberTech be liable for any indirect, incidental or consequential damages (including lost data, information or profits) sustained or incurred in connection with the use of, operation of, or inability to use Energy Central. Other terms of use may apply. Membership information is confidential and subject to our privacy agreement.