    RENEWABLE ENERGY AND STORAGE ISSUES - Installed capacity of Pumped Storage Projects (PSPs) in the country is 4745.6 MW and another 1500 MW capacity is under active construction - Union Power & NRE Minister Shri R.K. Singh


    March 15, 2023 - Indian Government News

     

      March 15 -- Government have taken several measures including the following, to address the vagaries in Renewable Energy (RE) generation caused by weather conditions and ensure smoother integration of RE generation with the grid:

        1. Construction of Intra-State and Inter-State transmission systems for evacuation of Renewable power.
        2. Setting up of Renewable Energy Management Centers (REMCs) for accurate forecasting of renewable power and for assisting grid operators to manage variability and intermittency of renewable power.
        3. Innovative products like solar-wind hybrid projects, Round the Clock RE projects, RE projects with energy storage systems and supply of RE power balanced with power from non-RE sources started to reduce intermittency.
        4. Implementation of Green Term Ahead Market (GTAM) and Green Day Ahead Market (GDAM) for sale of renewable power.
        5. Flexibility in Generation and Scheduling of Thermal/Hydro Power Stations through bundling with Renewable power and Storage Power.
        6. Notification of Energy Storage Obligation trajectory till 2029-30.

      As of now, Pumped Storage Projects (PSP) and Battery Energy Storage Systems (BESS) are the major feasible options to store RE. The PSPs have long gestation period, and their capacity is dependent on location, however, they have longer life. On the other hand, BESS have short gestation period, are non- dependent on location but limited by availability of minerals and technology.

      Under Tarif Based Global Competitive Bidding, issued by the Solar Energy Corporation of India Ltd., for setting up of 500 MW/1000 MWh standalone BESS pilot project, the lowest bid discovered is Rs 10,83,500 /- per MW/Month. To reduce the Levelized Cost of Storage, a viability gap funding scheme for 4,000 MWh of BESS has been announced in the Budget for the year 2023-24.

      As reported by Central Electricity Authority the present installed capacity of PSPs in the country is 4745.6 MW and another 1500 MW capacity is under active construction. The growth of PSPs in the country has been slow due to variety of factors, which include long gestation period, capacity being location dependent, requirement of Environment Clearance, etc.

      A detailed Plan titled “Transmission System for Integration of over 500 GW RE Capacity by 2030" has been prepared in consultation with States and other stakeholders by the Committee constituted under Chairperson, Central Electricity Authority by the Ministry of Power. The Plan was launched on 7th December 2022. Further, under the Green Energy Corridor Project, Intra-State Transmission Systems are being created with financial support from Central Government.

      This information was given by the Union Minister of Renewable Energy & Power Sh. R.K. Singh in the Rajya Sabha Today.

    TOP

    Other Articles - Utility Business / General


    TOP

       Home  -  Feedback  -  Contact Us  -  Safe Sender  -  About Energy Central   
    Copyright © 1996-2023 by CyberTech, Inc. All rights reserved.
    Energy Central® and Energy Central Professional® are registered trademarks of CyberTech, Incorporated. Data and information is provided for informational purposes only, and is not intended for trading purposes. CyberTech does not warrant that the information or services of Energy Central will meet any specific requirements; nor will it be error free or uninterrupted; nor shall CyberTech be liable for any indirect, incidental or consequential damages (including lost data, information or profits) sustained or incurred in connection with the use of, operation of, or inability to use Energy Central. Other terms of use may apply. Membership information is confidential and subject to our privacy agreement.