    The DEA issues permit for preliminary site investigations in the site Nordsøen I


    March 17, 2023 - Contify Energy News

     

      Danish Energy Agency issues permit to Energinet regarding initiation of preliminary site investigations for future offshore wind farms in the Nordsøen I-area in the North Sea. The site investigations will be initiated in Q2 2023 and will cover geophysical and geotechnical studies of the areas designated for potential offshore wind fields and possible cable corridors.

      Original Press Release:

      March 15 -- Danish Energy Agency issued the following news release:

      The permit is issued to Energinet who will begin the collection of relevant data and information in the area in second quarter of 2023.

      On 15 March 2023, the Danish Energy Agency issues permit to the Danish TSO, Energinet, regarding initiation of preliminary site investigations for future offshore wind farms in the Nordsøen I-area in the North Sea.

      The site investigations will be initiated in Q2 2023 and will cover geophysical and geotechnical studies of the areas designated for potential offshore wind farms and possible cable corridors, as well as marine biological studies to be carried out in the surrounding areas.

      With this permit, Energinet can gather relevant data concerning the identified sites. This data will contribute to mitigating risks for potential developers. A developer will also be able to use the results of the preliminary site investigations for the environmental impact assessment (EIA), which any concrete plans for establishing an OWF will have to undergo at a later stage. The issued permit does not grant rights to establish offshore wind farms in the area.

      Faster development of offshore wind towards 2030

      In Denmark, preliminary site investigations have traditionally been initiated based on a political agreement designating a specific sites for OWF development. However, Energinet’s preliminary site investigation for the Nordsøen I-area is being initiated prior to political agreements designating this site for OWFs. This is a result of a decision of the Climate Agreement on Green Power and Heat 2022 to initiate preliminary site investigations for all identified suitable OWF sites in order to fulfill the ambitions of more offshore wind by 2030.

      About offshore wind farms in the Nordsøen I-area

      * With the Danish Finance Act for 2022 it was decided to add 2 GW to the target capacity set by the Energy Agreement of 29 June 2018.

      * The Danish Energy Agency identified attractive offshore wind sites through the screening report on suitable marine areas that was published on 11 May 2022.

      * With the Climate Agreement on Green Power and Heat 2022 it was decided that an additional 4 GW offshore wind should be commissioned by the end of 2030. It was further decided decision to initiate preliminary site investigations for sites identified in the screening, including Nordsøen I.

      Source: Danish Energy Agency

      [Category: Energy Equipment & Services, Regulatory and Legal, ESG]

    TOP

    Other Articles - International


    TOP

       Home  -  Feedback  -  Contact Us  -  Safe Sender  -  About Energy Central   
    Copyright © 1996-2023 by CyberTech, Inc. All rights reserved.
    Energy Central® and Energy Central Professional® are registered trademarks of CyberTech, Incorporated. Data and information is provided for informational purposes only, and is not intended for trading purposes. CyberTech does not warrant that the information or services of Energy Central will meet any specific requirements; nor will it be error free or uninterrupted; nor shall CyberTech be liable for any indirect, incidental or consequential damages (including lost data, information or profits) sustained or incurred in connection with the use of, operation of, or inability to use Energy Central. Other terms of use may apply. Membership information is confidential and subject to our privacy agreement.