On May 19, 2023, the "Rooftop Distributed Photovoltaic Project" of our subsidiary "Shanwei Tianmao New Energy Technology Co., Ltd." was successfully connected to the grid for power generation. This project is the first distributed photovoltic project put into operation in Shanwei High-tech Zone. The photovoltaic project was jointly constructed by Shanwei Tianmao and Shanwei China Resources Energy Co., Ltd., with a total investment of more than 18 million yuan and a total installed capacity of 3.343MW.
Key Highlights:
* After the project is put into operation, the average annual power generation is about 4 million kWh, and the average annual replacement of standard coal is 1195.42 tons.
* During the 25-year design and operation period of the project, the total power generation is about 100 million kWh, and the total carbon dioxide emission reduction is 643,300 tons.
Original Press Release:
May 30 -- Zhongshan Tianmao Battery Co., Ltd. issued the following news release:
On May 19, 2023, the "Rooftop Distributed Photovoltaic Project" of our subsidiary "Shanwei Tianmao New Energy Technology Co., Ltd." was successfully connected to the grid for power generation . This project is the first distributed photovoltaic project put into operation in Shanwei High-tech Zone, which represents another "new chapter" for our company to explore the utilization of renewable green energy in Shanwei High-tech Zone, and to achieve the park's "double carbon" goal and high-quality development. "new start".
The photovoltaic project was jointly constructed by Shanwei Tianmao and Shanwei China Resources Energy Co., Ltd., with a total investment of more than 18 million yuan and a total installed capacity of 3.343MW. The construction will start at the end of December 2022. The construction period lasted for a total of 5 months and passed the acceptance of Shanwei Power Supply Bureau. On May 19, it was successfully connected to the grid for power generation. After the project is put into operation, the average annual power generation is about 4 million kWh, and the average annual replacement of standard coal is 1195.42 tons. During the 25-year design and operation period of the project, the total power generation is about 100 million kWh, and the total carbon dioxide emission reduction is 643,300 tons.
Mr. Lin Junpo, the chairman of the company, and Mr. Lin Junyang, the general manager, said that the construction of photovoltaic projects is in line with the company's vision and mission: First of all, Tianmao starts from itself, practices "green and energy saving", fully promotes energy conservation and emission reduction, and is committed to building To become a resource-saving and environment-friendly enterprise benchmark; secondly, Tianmao will continue to promote the optimization and upgrading of the industry, provide more durable, environmentally friendly, green and low-carbon power energy, actively promote the circular economy, and realize the utilization of comprehensive resources. Not only produces green and safe new energy products, but also contributes to the low-carbon and environmental protection of the society, becoming a responsible enterprise that provides green and safe services to the society. At present, the Zhongshan Tianmao photovoltaic project of the head office is also under construction, and it is expected to be connected to the grid for power generation by the end of October 2023.
Tianmao will take this as a starting point. With the rapid development of science and technology and the urgent market demand for clean energy, we have a long way to go, and we will work together with all parties in the society to achieve the national grand strategy of "carbon peak, carbon neutrality" The goal and the development of green and low-carbon energy with Chinese characteristics contribute to Tianmao!
Disclaimer: The Above Content is Auto-Translated
Source: Zhongshan Tianmao Battery Co., Ltd.
[Category: Events]