    Alberta Utilities Commission Provides Update Regarding Inquiry Into Development Of Electricity Generation In Alberta


    September 14, 2023 - By Deirdre A. Sheehan, Jacob Sadikman, Paula Olexiuk, Simon Baines and Bryce Kustra

     

      Recently, we discussed the Government of Alberta's Generation Approvals Pause Regulation and direction that the Alberta Utilities Commission (AUC) is taking as it holds an inquiry into renewable electricity generation. The AUC issued supplemental information requirements for renewable electricity generation projects (discussed here) on September 6, 2023 and on September 11, 2023, issued Bulletin 2023-06 [PDF], providing further details regarding the inquiry, which will consider the ongoing economic, orderly and efficient development of electricity generation in Alberta (the Inquiry).

      The Inquiry will review the role of municipal governments in land selection for project development and review and will also consider:

      1. The development of power plants on specific types or classes of agricultural or environmental land.
      2. The impact of power plant development on Alberta's viewscapes.
      3. The implementation of mandatory reclamation security requirements for power plants.
      4. The development of power plants on lands held by the Crown in Right of Alberta, and
      5. The impact of increasing growth of renewable energy resources on the generation supply mix and electric system reliability.

      These issues will be considered in two separate modules (Module A and Module B). Module A will consider issues one to four while Module B will consider issue five.. While the AUC has released details respecting Module A (discussed below), details respecting Module B are expected to be announced in the near future.

      Module A

      The AUC will issue a notice through the eFiling system with additional information regarding the process and timelines for the Inquiry.

      Interested parties may participate in Module A by: (i) completing an online survey; (ii) providing submissions in writing; and (iii) providing submissions orally at an in-person session. The AUC will distribute the online survey and comment matrix for parties to use when preparing written submissions. The dates and venues of in-person sessions are still to be determined, but are expected to take place in several locations across Alberta.

      The forthcoming notice will provide further instruction on how interested parties may participate in the Inquiry, including procedures for providing written submissions, completing the online survey, attending in-person sessions for oral submissions, and submitting any comments or questions.

      The AUC also will be retaining experts to prepare reports related to the issues under review. These reports will be made publicly available on the AUC's eFiling system for interested parties to review and comment on.

      The AUC further anticipates that it will hold an oral hearing to question select participants on their pre-filed submissions. The AUC will identify and request the attendance of specific parties it seeks to question. The oral hearing is expected to take place in December, 2023.

      The following is the preliminary schedule, and the AUC has indicated that additional details will be coming soon:

      Process step

      Timeframe

      AUC notice with additional updates/participant information

      Mid-September

      Oral submissions (in-person)

      Late October to mid-November

      Written submissions

      Mid to late November

      Reply submissions

      Early December

      Oral hearing

      Mid December

      Deadline for the AUC to submit report to the Minister of Affordability and Utilities

      March 29, 2024



      Osler will continue to monitor these developments closely.

      The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

      Deirdre A. Sheehan

      Osler, Hoskin & Harcourt LLP

      Suite 2500, Toronto Dominion Square

      TransCanada Tower

      450 - 1st St. S.W.

      Calgary

      Alberta

      T2P 5H1

      CANADA

      Tel: 4163622111

      Fax: 4168626666

      E-mail: jebrown@osler.com

      URL: www.osler.com

    TOP

    Other Articles - Utility Business / General


    TOP

       Home  -  Feedback  -  Contact Us  -  Safe Sender  -  About Energy Central   
    Copyright © 1996-2023 by CyberTech, Inc. All rights reserved.
    Energy Central® and Energy Central Professional® are registered trademarks of CyberTech, Incorporated. Data and information is provided for informational purposes only, and is not intended for trading purposes. CyberTech does not warrant that the information or services of Energy Central will meet any specific requirements; nor will it be error free or uninterrupted; nor shall CyberTech be liable for any indirect, incidental or consequential damages (including lost data, information or profits) sustained or incurred in connection with the use of, operation of, or inability to use Energy Central. Other terms of use may apply. Membership information is confidential and subject to our privacy agreement.